Project Overview:
|
||
The Solution:A project manager from FSCG with knowledge of the OPG
industry and expertise in fast-track projects was dedicated to GOC to
provide technical support and a single source procurement service, 24
hours a day. This enabled specifications to be agreed, goods ordered and
shipped on a daily basis without delay. |
|||
Summary:By taking advantage of our geographical position to
offset time differences and positioning ourselves as a central communications
point between the engineering services and client 24 hours a day we were
able to supply a tailor made procurement and expeditor service offering
the client cost and time savings with the guarantee of the correct goods
arriving on time. Throughout the duration of the project two dedicated lorries and numerous airfreight shipments were made to Azerbaijan to facilitate the installation. The plant was commissioned in late December and started pumping on time. |
|||